Undisclosed Location | Feb 2022 - Oct 2022



This project required four months of pre-mobilization planning including development of work, safety, industrial hygiene, and engineering plans to demolish and repair interior concrete walls within critical infrastructure areas for the client. Following demolition activities, JBrennon et al reconstructed interior concrete walls, infilled existing door openings, and built a concrete pad for future equipment installation.




 